We’re pleased to share the latest construction update at our luxury condominium at No. 358, High-Level Road, Nugegoda .
The concreting of Lift Walls 03 and 04 between the 3rd Level Car Park and Mezzanine Floor has been completed for grids L to Q .
Additionally, 12 structural columns from the Mezzanine to the First Residential Floor have been caste within grids F to L . Slab and beam concreting for the 2nd Level Car Park (grids D to F) is also done, while shoring continues in grids A to D (Main Entrance Area).