Mezzanine Slab, Beam-Column & Pile Cap Concreting Underway – No. 358, High-Level Road, Nugegoda

Share your love

We are pleased to announce that construction at our luxury oceanfront condominium at No. 358, High-Level Road, Nugegoda is progressing on schedule.

The mezzanine slab and beam-column works for selected grids (F to D) are currently underway, while pile cap concreting for grids (A to D) has also commenced. This marks another significant milestone in delivering a prestigious lifestyle destination that blends sophisticated design with engineering excellence.

These ongoing advancements reflect our unwavering commitment to delivering a premium-quality living experience, on schedule and with precision.